Skip to content
Haiyun Flour Milling Systems
Yuncheng 500 t/d plant

Turnkey — twin-line design, supply, installation, commissioning · 2022

Yuncheng 500 t/d flour plant

The largest plant delivered to date: two parallel 250 t/d lines with shared intake, separate milling floors and a common packing hall, running at 65–70 kWh/t.

  • 60+ years manufacturing
  • 10–500 t/d capacity range
  • 100+ patents
  • Turnkey commissioning

Capacity

500 t/d

Installed power

1,650 kW

Specific power

65–70 kWh/t

Lines

2 × 250 t/d

Building

60 × 10 × 24 m

Extraction

77% patent

郓城 500 吨面粉厂 · Yuncheng County, Heze, Shandong, China

The brief

The client is a Shandong flour group supplying national retail brands. The requirement was 500 t/d with the ability to run one line while the other is under maintenance — a continuity requirement that rules out a single 500 t/d train.

Two parallel 250 t/d lines sharing intake, wheat storage and packing is the standard solution, but it creates its own problems: shared intake becomes the single point of failure, and shared packing means a packing stoppage stops both lines.

What constrained the design

Four constraints that shaped the plant more than the capacity figure did.

01

Continuity without duplication

Two milling lines, but a single intake and a single wheat cleaning house. The intake is sized at 210 t/h — enough to fill both lines' tempering bins in a single shift — and the cleaning house is duplicated internally so one half can be maintained while the other runs.

02

Packing as the bottleneck

At 500 t/d the plant produces 385 t of flour per day. That is 15,400 × 25 kg bags, or roughly 12 bags per minute continuously. Three packing lines were installed, not two — one more than the arithmetic requires, because a single packing stoppage otherwise backs flour up into both sifters within 40 minutes.

03

Power supply

1,650 kW installed draws roughly 1,400 kW average, which is a 2,000 kVA transformer with margin. The local supply required a dedicated 10 kV feeder and a 2,500 kVA transformer. Staggered starting was mandatory: simultaneous start of both lines would have created a demand spike that set the monthly charge for the whole plant.

04

Building height

24 m to the eaves, 27.5 m total. Two independent gravity flow paths stacked in one building, with separate sifter floors so a sifter intervention on one line does not affect the other.

What was built

Intake 80 t weighbridge, 210 t/h receiving capacity, two roofed pits, automatic sampling.
Storage Six 2,000 t silos (12,000 t total, ~18 days), all aerated at 0.25 m³/min/t, with temperature cables and a blending system across four of them.
Cleaning Two 30 t/h lines, each internally split so half can be isolated for maintenance. Drum sieve, self-balancing screen, gravity destoner, two scourers, washer-destoner, magnetic separation, dampening to 16.2%.
Tempering Eight bins per line, 24-hour tempering. Independent water and heat control per line.
Milling 4B5M1S1T per line on twelve FMFQ(S) double roller mills per line. 24 roll mills total, 1,000 mm rolls.
Sifting Three FSFG high square plansifters per line, 68 m² per line, 136 m² total — 0.74 t/d per m².
Purification Two FQFD purifiers per line, 8 sections each, with independent aspiration and separate semolina handling.
Packing Three LCS lines, 14 bags/min each, with automatic palletising and a 5 kg consumer line.
Dust collection Six pulse-jet collectors, 240 m² total cloth area, all vented outdoors with explosion venting and isolation.

Measured outcome

Performance acceptance ran at 507 t/d combined over 72 hours, 77.1% extraction, 66.8 kWh/t. Both lines ran continuously with zero unplanned stops during the test.

Twelve months of operation showed the plant at 68.2 kWh/t average — slightly above the acceptance figure, attributable to running at 88% average capacity rather than 100%.

The third packing line earned its cost twice in the first year. Each time one line stopped for a bag sealer repair, the remaining two absorbed the output with a 40-minute buffer rather than forcing a milling line down.

What we would do differently

The honest section. Every project teaches something that was not in the specification.

  • Continuity requirements drive the architecture more than capacity does. A single 500 t/d train would have been 12–15% cheaper in capital and would have had a single point of failure at every stage.
  • Packing capacity should be sized at 130% of milling output, not 100%. The cost of a third line was roughly 1.5% of plant capital and it protects the whole plant against the most frequent stoppage.
  • Sub-metering at line level, not just plant level, was specified. It is what allowed the client to identify that line 2 was drawing 4% more power per tonne than line 1 within the first month — traced to a sifter drive misalignment that would otherwise have run for a year.

Next step

Planning a plant of this size?

Send us your target capacity, wheat specification and site constraints. We will tell you what a plant like this one would need — and what we would change if we built it today.